Laurie Johnson from DLZ presented a study of CARES Act funding to the Marshall County Commissioners Tuesday morning and what projects would benefit the county most with the use of the funding.
Continue readingLaurie Johnson from DLZ presented a study of CARES Act funding to the Marshall County Commissioners Tuesday morning and what projects would benefit the county most with the use of the funding.
Continue readingThe Marshall County Commissioners reviewed a letter of engagement with DLZ this month concerning a study on the county’s HVAC and air quality systems.
Continue readingThe deed and easement paperwork for the mitigation site around Bridge No. 89 in Marshall County is nearly complete.
Continue readingThe Marshall County Commissioners will consider a speed limit and stop sign ordinance on Veterans Parkway and Linden Road. They will also discuss the 2018 road plan for Underwood Road in Union Township and 12th Road in Bourbon Township.
Construction on the Hickory Road bridge over the Yellow River in Marshall County will begin Monday, March 26.
To accommodate the planned construction, Hickory Road between 7B Road and 8B Road will be closed through a tentative date of July 7. The proposed detour utilizes 9B Road, Fir Road and 7th Road.
The Hickory Road Bridge project was let for bid on Wednesday. Laurie Johnson from DLZ told the Marshall County Commissioners on Monday that eight potential prime companies were set to bid the project.
In the meantime, Johnson said trees will need to be removed to make way for the project.
Marshall County Highway Administrator Laurie Baker presented the commissioners with a contract between the county and DLZ concerning the Hickory Road bridge. The contract includes the construction inspection of the bridge and the off-site wetland mitigation. The commissioners did approve a contract with DLZ Engineering not to exceed $186,360.
Laurie Johnson from DLZ provided an update on the pre-construction on the Hickory Road Bridge project.
One Marshall County bridge is almost complete while another is in the design phase.
Ben Beer from USI Consultants told the Marshall County Commissioners on Monday that Bridge #174, or Apple Road Bridge, is nearly complete.
“They should have everything completed this week,” said Beer. “They’re paving and putting up guardrail and seeding and then they’ll be out of there. There are no change orders. Everything was within budget.”
The Marshall County Commissioners will discuss the construction of a multi-purpose building at the Marshall County Fairgrounds in Argos when they meet this morning.
Shannon McLeod will be before the governing body to discuss the project spearheaded by the Marshall County 4-H Fair Association. The association was applying for an OCRA grant in the amount of $500,000 to assist in the construction of the building that the members hope will host many functions including wedding receptions, meetings and other community-type gatherings. The county will act as a pass-through vehicle for the purpose of obtaining the grant. County Attorney Jim Clevenger will present a memorandum of understanding between the county and the association that states that the county is not financially liable for this project.
The Marshall County Commissioners received an update on the plans for the Bridge 81, or Hickory Road, project.
Laurie Johnson from DLZ reminded the commissioners that the wetland mitigation documents will be presented to them at their next meeting for approval. The Plymouth Board of Public Works and Safety approved the paperwork at their last meeting that allows the county to maintain the grounds for ten years and then it will go back into the possession of the city.
Apple Road in Marshall County is closed so crews can demolish the Apple Road bridge.
LaPorte Construction is doing the bridge work. The commissioners approved a bid from the company in March in the amount of $274,774.68 to replace the bridge.
Bridge #174, or Apple Road bridge, is on Apple Road over the Yellow Creek, north of State Road 25 before the railroad tracks. Workers have a 75-day window in which to complete the project.
The work on getting paperwork done for the upcoming bridge replacement project on Hickory Road continues with various reports conducted by engineering firm DLZ.
Laurie Johnson from DLZ told the Marshall County Commissioners this week that the archaeological report is complete and approved by INDOT and no project impediments have been identified on the grounds. Title work for the mitigation site has been received and the permit for waterway construction will be reviewed by the Indiana Department of Natural Resources.
Preparations for the Hickory Road Bridge replacement project continue to move ahead. Laurie Johnson with engineering firm DLZ told the Marshall County Commissioners Monday the paperwork on the final right-of-way parcel was expected by the end of this week. Continue reading
The Hickory Road bridge replacement is moving closer to getting underway. Continue reading