The long-awaited Candy Lane Storm Sewer project in Plymouth is underway.
Continue readingBids for Plymouth’s Candy Lane storm sewer project came in higher than expected. Five bids were opened during Monday’s board of works meeting. Clerk-Treasurer Jeanine Xaver says they ranged from $1,047,000 up to $1,278,000, not including some optional work.
Continue readingThe Plymouth Board of Works is expected to award a bid for the spring street and sidewalk projects tonight. That will include work on portions of Randolph Drive, Stanley Drive, Walnut Street, Madison Street, Kingston Road, Lemler Lane, and Chester Street. The five bids opened earlier this month ranged from just under $636,000 to more than $858,000.
Continue readingPlymouth Utility Superintendent Donnie Davidson asked permission of the Plymouth Board of Public Works and Safety to move forward in soliciting bids for the Candy Lane Storm Sewer project.