E&B Paving will be working to mill and pave several streets in Plymouth over the next week.
All streets will be milled at a five inch depth with three inches of an asphalt base to be placed the same day. Another schedule will be sent out to list when the final two inches of asphalt surface material will be applied.
There will be no parking on the streets during these operations and E&B Paving crews will be notifying all homes and businesses of the schedule. They will do the best they can to accommodate access to and from drives.
Operations begin today on Crimson Lane from the west end to Hillcrest Avenue and Hillcrest Avenue from Red Oak Court to Winding Oak Drive.
Crews will be on Felix Place from Pearson Place to Hillcrest Avenue on Saturday, October 1
Work on West Garro Street from Ben Lane to 7th Street and from West Garro to West Laporte will take place Monday, October 3. Crews will be on 5th Street from Harrison Street to Jefferson Street on Tuesday, October 4, 5th Street from Jefferson Street to railroad Wednesday, October 5, on Washington Street from Michigan Street to Water Street Thursday, October 6, and cemetery milling and compaction on Friday, October 7.
The schedule could change depending on the weather.