Plymouth Street and Sidewalk Projects to Begin Soon

Street and sidewalk projects will begin soon in the City of Plymouth.

The Plymouth Board of Public Works and Safety members received an update from City Engineer Rick Gaul during their Monday night meeting that a pre-construction meeting is scheduled for August 16 and work should start soon after that meeting. 

E&B Paving was the lowest bidder to do the work this year at a cost of $446,816.40. 

This year’s street projects include mill and fill projects on Fifth from Lake Ave. to the railroad tracks, Westgate from Hillcrest to State Road 17, Dickman from the dead end to Webster, Webster from Angel to Dickman, and Laporte from East Street to Kingston.  A base reconstruction with hot mix asphalt is planned on Seventh from Harrison to Beerenbrook.  

Mill and fill operations will be conducted on the cemetery street addition projects.  A mill in place with hot mix asphalt surface will be done at the cemetery old addition phase one.

The last project includes Packard Woods Senior Center parking lot.