With one project finished, another wrapping up and one right on schedule, the Triton School Corporation’s bond projects are coming along nicely.

Superintendent Jeremy Riffle reported that the HVAC installation project at the elementary school is entirely done. Staff members continue to make minor adjustments to regulate temperatures for the classrooms.

He added that the roof project at the high school should be complete this week. Crews are just finishing up some trim about the building and final clean-up.

Riffle also shared that school board members got a tour of the Auxiliary Gym prior to their meeting Monday evening. Superintendent Riffle said that the project is coming along on schedule and the projected completion date is January 24th, 2019.