There are some additional students attending the Triton Community School Corporation this school year, according to Superintendent Jeremy Riffle. Riffle said compared to last year’s average daily membership (ADM) count, there are 20 more students enrolled at Triton for the 2018-19 school year.
Superintendent Riffle also mentioned that the ongoing projects happening at Triton are either on track or ahead of schedule.
The HVAC system has been installed at the Elementary School. It is operational and staff members are currently working to regulate the temperatures in classrooms.
Riffle said that the roof project at the Junior/Senior High school is nearing completion. The portions that remain are about 2 weeks away from being finished.
Riffle added that there has been some major progress with the Auxiliary Gym. Last week, representatives from Michael Kinder and Sons, the construction company responsible for the project, shared that the structural steel has been placed and that exterior walls will be going up soon.
Superintendent Riffle said the estimated completion date for that project is around January 20th, 2019.