New Lincoln Junior High School Construction Remains On-Schedule

East elevation of new Lincoln Junior High School (photo from Plymouth School Board’s November 5 project update)

Progress continues at the new Lincoln Junior High School, despite some wintry weather recently. Project Manager Derek Anderson told the Plymouth School Board Tuesday that brickwork is about 60 to 70 percent complete. Inside, the walls are up in the future administrative offices, and all of the kitchen walls are done.

Continue reading

Roofing Installation Continues at New Lincoln Junior High School

Future boiler room area of new Lincoln Junior High School. (photo from Plymouth School Board’s July 2 project update)

The new Lincoln Junior High School continues to take shape. In an update to the Plymouth School Board last week, Project Manager Derek Anderson said crews have started installing the roof over the two-story classroom wing, and most of the elevated slabs are complete. Concord Roofing Pros – Roofing Services in Concord, NC offers the best installation package which comes with affordable price with skilled workers working throughout the installation.

Continue reading

Lincoln Junior High School Construction Remains On-Schedule Despite Weather Challenges

Future two-story classroom wing of new Lincoln Junior High School. (photo from Plymouth School Board’s Dec. 11 project update)

Crews working on the new Lincoln Junior High School had to deal with colder-than-average temperatures last month. Project Manager Derek Anderson told the Plymouth School Board Tuesday that weather slowed down construction slightly.

Continue reading

Foundation, Masonry Work Continue at New Lincoln Junior High School

wall of future gym at new Lincoln Junior High School (photo from October 2 project update presented to Plymouth School Board)

Crews working on Plymouth’s new Lincoln Junior High School building are busy preparing the site for winter. Project Manager Derek Anderson told the Plymouth School Board Tuesday that 95 percent of the footings and foundations have been poured for the two-story classroom wing.

Continue reading

Masonry Work to Start Soon, As Lincoln Junior High Building Project Progresses

Site work for the new Lincoln Junior High School has progressed steadily in the past month. Project Manager Derek Anderson told the Plymouth School Board Tuesday that much of the work is still underground. He said crews were able to complete the new storm lines before school started. The rest of the site utilities should be wrapping up in the next couple weeks.

Continue reading