Project bids for extension work needed on a West Lake Avenue water main were considered during the Plymouth Board of Public Works and Safety meeting on Monday. Plymouth Utility Superintendent Donnie Davidson mentioned that the original engineer’s estimate for the project was about $187,450.
He also explained what the project will entail, “It’s an 8-inch water main that will go from where the Montgomery Apartments are, across from the hospital, and it will go around the corner and it will serve the Autumn Trace Assisted Living Facility and will dead-end at their west driveway.” Continue reading



The Culver Town Council members took action Tuesday night to move the Sand Hill Farms construction a little further along the process.
Four bids were received by the Plymouth City Council Monday night for the Richter Road water main extension project.