Argos Town Council members were provided with an update about ongoing Community Crossings projects when members met Wednesday evening.
Town Superintendent Jamie Lindstrom noted that E&B Paving has been conducting work on Woodland Trail and Westview Court. He said there’s a possibility they could be finished up with those projects by next week.
Superintendent Lindstrom shared that he expects crews to get started on the Colonial Estates project on Monday. That project was awarded to the company Walsh and Kelly back in March.
As a reminder, this project will involve, not only paving Constitution, Freedom and Independence Streets, but it will also include installing curbs, sidewalks and drainage within the subdivision.
Lindstrom mentioned that it will likely take around 7 weeks to complete the Colonial Estates project.