Plymouth Wastewater Project Comes to a Close

The Plymouth Wastewater Treatment facility improvement project is finally complete.

Utility Superintendent Donnie Davidson told the Plymouth Board of Public Works and Safety members this week that Kokosing Industrial recently finished punchlist items. Closeout documents will be presented to the members at their next meeting where a change order will need to be approved. Davidson said one deduct change order has yet to be compiled as the final financial aspects are totaled.

In the meantime, an open house is scheduled for Saturday, Oct. 20 from 9 a.m. to 11 a.m. where residents can tour the facility and see what upgrades were made at the plant on Oakhill Avenue.