Plymouth Water Treatment Plant Work Progressing

Plymouth IndianaWork on the exterior of Plymouth’s Ledyard Water Treatment Plant should be finished before winter weather arrives. City Utility Superintendent Donnie Davidson told the board of works last night demolition work is ongoing on the west side of the structure. It’s part of a three-phase project.

Davidson advised the board the water main extension between West LaPorte Street and Oak Hill Avenue is substantially complete. So is the Ledyard storage building, which is also operational. Mayor Mark Senter signed letters of substantial completion for the water main extension and storage building phases. A few final punch list items remain on both projects.