Street Reconstruction Projects Scheduled in Plymouth

Street reconstruction work as part of the city of Plymouth’s mill and fill projects is set to begin today. Workers are scheduled to sawcut six driveways and remove curb in the cul-de-sac on Marigold Court. Concrete curb construction will start tomorrow. During that time, residents will have access to their driveways except for a few days when the concrete is curing. Notes will be placed in the mailboxes of affected residents.

On Tuesday intersection ramp reconstruction will start on Pennsylvania Avenue from Liberty to Kingston. Concrete crews will be following on Pennsylvania.

Wednesday crews will start intersection ramp reconstruction on Garro Street from Walnut to Center Street and on Madison from Center to Michigan. Concrete crews will be following on Garro and Madison after they finish Pennsylvania.

Thursday intersection ramp reconstruction will begin on Plum Street from LaPorte to Washington. Concrete crews will follow after they finish on Garro and Madison.

Asphalt milling and paving schedules will be released closer to their respective start dates. The schedules are subject to weather and unforeseen circumstances. Motorists are urged to drive carefully through the work areas or avoid them if possible.