Plymouth residents should expect to see some road construction over the next few days. Contractor Walsh and Kelly has released its schedule for work on the city’s 2016 street projects.
Concrete removal continues today on Plum Street. Then, concrete placement will take place through Friday, followed by milling on Saturday and paving Sunday and Monday.
Meanwhile, the park roads have milling and paving work taking place today. On Memory Court, milling work takes place today, followed by paving tomorrow. Milling work moves to Nutmeg Road and Fairfield Boulevard tomorrow, followed by paving work on those two streets Friday.